Inspection Sequence Checklist

The ordered inspections a project needs, each with its triggering section.

New single-family dwelling

  1. Footing MPLS § 91.130After excavation and forms, before concrete
  2. Foundation MPLS § 91.130After foundation walls, before backfill
  3. Rough framing MPLS § 91.130After roof, framing, fire-blocking, before cover
  4. Rough mechanical / plumbing / electrical MPLS § 91.140Before insulation and drywall
  5. Insulation MPLS § 91.130After rough-ins pass, before drywall
  6. Final MPLS § 91.150When complete and before occupancy

Call for each inspection and pass it before covering the work. Sequence can vary with scope — confirm with your plan reviewer.

Need a case this tool doesn't cover? Ask in chat

Reference only. This is general information, not legal advice, and not engineering advice or an official determination of code compliance. These figures are hand-transcribed from public sources and may be inaccurate or out of date. Independently verify against the current code and with the authority having jurisdiction (AHJ) before you build, buy, or file — you rely on these results at your own risk. Indexed from public Minneapolis municipal sources.

Indexed from public municipal sources. General information only — not legal, engineering, or professional advice. Last indexed 2026-06-15.
Answers and figures are AI-generated or hand-transcribed and may be inaccurate or out of date. Independently verify against the current code and with the authority having jurisdiction before construction or filing. Use is at your own risk.
A reference work by Telesto Tech · Denver, CO
citycode